28 of the 61 industrial and warehouse buildings over 1,000 m² in Havant with an EPC are rated C to E: 936k sq ft (86,919 m²) of floorspace that meets today's E minimum but falls short of the proposed EPC B standard.

Free. No card needed.

Havant in figures

EPC register, snapshot 30 Sep 2026

Rated C to E
936k sq ft86,919 m² in 28 buildings
Rated F or G
0 buildingsNone below today's E minimum
Rated A+ to B
33 buildingsAlready at the proposed standard
Share below B
46%Of 61 buildings over 1,000 m². England and Wales: 70%

Havant has the 256th most floorspace rated C to E of 316 local authorities in England and Wales, and the 42nd most of 64 in the South East.

EPC rating mix

Share of buildings over 1,000 m², by latest EPC rating

  • Havant61 buildings
  • South East5,119 buildings
  • England and Wales38,148 buildings
Key: Rated A+–B: At B or better alreadyRated C–E: Meets today's E minimum, short of BRated F–G: Below today's E minimum

Latest certificate per building from the government's EPC register, snapshot 30 Sep 2026. Industrial and warehouse uses (B2 and B8), floor area over 1,000 m² as declared on the EPC; 1 m² is 10.7639 sq ft. How we count it

What stands out in Havant

Compared with the other 63 local authorities in the South East and with England and Wales, from the same EPC register snapshot.

  • None of its buildings over 1,000 m² is rated F or G, as in 30 of the other 63 local authorities in the South East.
  • Most of its floorspace rated C to E, 55% or 511k sq ft (47,502 m²), is in 24 buildings of 1,000 to 5,000 m².
  • Unusually, its smaller buildings do better: 54% of those of 1,000 to 5,000 m² are rated B or better, against 50% of the 6 over 10,000 m².
  • 14 of its 28 buildings rated C to G (50%) have an EPC that has lapsed or is estimated to lapse before 2031, against 54% across England and Wales; 5 have already lapsed.
  • 7 of its 17 C-rated buildings (41%) have an asset rating of 51 to 60, within 10 points of band B: 381k sq ft (35,416 m²) of floorspace. Across England and Wales it's 37%.
  • Storage and distribution (B8) makes up 69% of its buildings over 1,000 m², against 58% across England and Wales.
  • In the 12 months to 30 Sep 2026, 7 industrial and warehouse buildings of any size here had an EPC lodged to be let and 11 for a marketed sale, 18 in all: the 22nd fewest of 64 local authorities in the South East.
  • The recommendation lodged most often on its certificates rated C to G is “Consider installing solar water heating” (EPC-R3), on 19 of 28 buildings.

Every rating, A+ to G

Havant's 61 industrial and warehouse buildings over 1,000 m² by latest EPC rating, beside the South East and the whole of England and Wales.

By latest EPC rating

Share is of buildings over 1,000 m² in each area.

Havant: industrial and warehouse buildings over 1,000 m² by latest EPC rating, with the share in each band and South East's and England and Wales's
RatingBuildingsFloor areaShareSouth EastEngland and Wales
A+8273k sq ft25,390 m²13%3%2%
A16772k sq ft71,679 m²26%13%10%
B9419k sq ft38,900 m²15%22%19%
C17610k sq ft56,646 m²28%35%36%
D10314k sq ft29,152 m²16%21%22%
E112k sq ft1,121 m²2%6%9%
F00 sq ft0 m²0%1%1%
G00 sq ft0 m²0%1%2%

Within 10 points of B

Rated C with an asset rating of 51 to 60. Band B ends at 50.

7 buildings

Of 17 rated C (41%), with 381k sq ft (35,416 m²) of floorspace. England and Wales: 37% of C-rated buildings.

By building size

Floor area as declared on the EPC.

Havant: industrial and warehouse buildings by floor area
Floor areaBuildingsRated B or betterC to E floor area
Over 1,000 to 5,000 m²5254%28 of 52511k sq ft47,502 m²
Over 5,000 to 10,000 m²367%2 of 366k sq ft6,090 m²
Over 10,000 m²650%3 of 6359k sq ft33,327 m²

Certificates and lettings

An EPC lasts 10 years, and a valid one is needed to let or sell. We estimate expiry as the lodgement date plus 10 years.

When the certificates lapse

Buildings over 1,000 m², by when their latest EPC lapses, at 30 Sep 2026.

Havant: when each building's latest EPC lapses (estimated)
EPC lapsesAll buildingsRated C to GC to G floor area
Already lapsed65336k sq ft31,187 m²
Rest of 20261112k sq ft1,155 m²
In 2027100 sq ft0 m²
In 20281122k sq ft2,067 m²
In 202994107k sq ft9,982 m²
In 20303365k sq ft6,014 m²
2031 or later4014393k sq ft36,514 m²

New EPCs in the last year

Industrial and warehouse buildings of any size whose latest EPC was lodged in the 12 months to 30 Sep 2026, by the reason on the certificate.

To let
7buildings
Marketed sale
11buildings
New build
4buildings
Other reasons
2buildings

24 in all: 29% to let, against 56% across England and Wales. How the daily feed works

Uses, heating and recommendations

What the buildings are used for, how they're heated, and what assessors recommended on the certificates of those rated C to G.

By use

Use from the EPC's property type.

Havant: buildings over 1,000 m² by use, from the EPC's property type
UseBuildingsB or betterC to EF or GC to E floor area
Storage and distribution (B8)4226160538k sq ft49,947 m²
General industrial (B2)197120398k sq ft36,972 m²

By main heating fuel

As recorded on each building's latest EPC.

Havant: buildings over 1,000 m² by main heating fuel on the EPC
Main heating fuelBuildingsShareEngland and Wales
Natural gas3456%53%
Grid supplied electricity2744%37%

What assessors recommend

The five most common on the latest certificates of its 28 buildings rated C to G, in the register's wording. A recommendation is the assessor's, not a requirement.

  1. 01

    Consider installing solar water heating.

    EPC-R3. On 19 of 28 buildings (68%)

  2. 02

    Add optimum start/stop to the heating system.

    EPC-H7. On 15 of 28 buildings (54%)

  3. 03

    Consider replacing T8 lamps with retrofit T5 conversion kit.

    EPC-L5. On 15 of 28 buildings (54%)

  4. 04

    Consider installing PV.

    EPC-R4. On 15 of 28 buildings (54%)

  5. 05

    Consider installing building mounted wind turbine(s).

    EPC-R2. On 14 of 28 buildings (50%)

How Havant compares

Havant has less than 0.1% of the industrial floorspace rated C to E in England and Wales. 46% of its buildings over 1,000 m² are below B, against 63% across the South East and 70% nationally.

Against the region and the country

Havant against the South East and England and Wales: industrial and warehouse buildings over 1,000 m²
AreaOver 1,000 m²Rated C to EC to E floor areaRated F or GShare below B
Havant6128936k sq ft86,919 m²046%
South East5,1193,153101.6m sq ft9,439,390 m²6663%
England and Wales38,14825,6191.01bn sq ft94,020,657 m²1,03770%

Nearby in the South East ranking

Local authorities ranked next to Havant in the South East by floorspace rated C to E
RankLocal authorityC to E floor area
40Thanet953k sq ft88,553 m²
41Worthing952k sq ft88,415 m²
42Havant936k sq ft86,919 m²
43Dover924k sq ft85,823 m²
44Sevenoaks912k sq ft84,749 m²

What the 2031 proposal means

In June 2026 the government said it intends that privately rented non-domestic buildings over 1,000 m² reach EPC B from 2031, where cost effective. It needs secondary legislation, so for now it's a proposal, not law. What the proposal means

  • C to E: fine today, short of B

    Havant has 28 buildings over 1,000 m² rated C to E. They meet today's E minimum, but would fall short of B if the proposal becomes law while they're let.
  • F or G: below the minimum already

    No building over 1,000 m² in Havant has a latest EPC rated F or G.
  • Where cost effective, and only when let

    The 7-year payback test and the exemptions remain. Owner-occupied buildings are counted too, as an EPC can't say whether a building is let. Local weights and measures authorities enforce the rules. MEES in plain English
  • Ratings change at renewal

    14 of Havant's buildings rated C to G have an EPC that has lapsed or is estimated to lapse before 2031. Each needs a new certificate before it's let or sold, and the new rating may differ.

Go building by building

  • One building at a time

    Search by postcode or estate name for each industrial building's rating, floor area, certificate expiry and whether it's over 1,000 m². Free, and you can save five buildings to a free account.

    Check a building in Havant
  • The whole local authority

    Professional's area screens list every industrial building over 1,000 m² in a local authority with its rating and expiry, for 3 local authorities. £79 a month, or £790 a year.

    Compare plans

The Industrial EPC Weekly

Last week's new industrial EPCs by region, every Monday. Free.